Principal Contractor – Extension of car parking area from 3 to 5 bays.

Programme: 4 weeks

Value: £100k

 

WGP Maintenance Ltd provide structured project management individually tailored to our clients’ requirements. Our processes are laid out in our ISO 9001 & 14001 documentation along with our customer relationships management software. This supports all aspects of planning and construction from inception to completion, allowing us to carry out high quality work with minimal disruption to day-to-day operations.


Client requirements

We took on the role of Principal Contractor for a hospital car parking extension. The project was to enlarge the parking area from 3 to 5 parking spaces and included an element of extensive trenching, the installation of a 3-phase supply from the plant room, all the surface finishes, line marking, and the installation of lockable drop-down bollards.

WGP Maintenance Ltd coordinated the California Bearing Ratio (CBR) testing to evaluate the strength and bearing capacity of the ground prior to commencement of works. The client required the new bays to withstand the load of a customised mobile facility trailer.

 

Want to know more?

Contact us

Contact Us

Get in touch with our friendly team to find out more

About yourself
Contact details
About Your Project

By submitting my data I agree to be contacted.